HYBRID · 5 chapters · CHAPTER 04

Hybrid Planning & Dependencies

Plan the interfaces, not just the tasks

Chapter 04 of 5Read as a practical lesson

The hardest hybrid problem is often the handoff

An Agile team can move quickly while a predictive dependency remains fixed. That dependency becomes a planning boundary.

QuestionPractical answer
Agile streamIterative UX and feature development
Predictive streamData migration and production cutover
InterfaceFeature readiness must meet migration/cutover criteria
GovernanceIntegrated readiness review before release

Use multiple planning horizons

Maintain a high-level integrated roadmap for major commitments, then allow each workstream to plan at the level appropriate to its uncertainty.

01Integrated roadmap
02Workstream plan
03Iteration plan
04Dependency review
05Release readiness

Watch for hidden queues

If the Agile team completes work faster than testing, security review or deployment can absorb it, the system is not actually getting faster. Hybrid planning must include the full flow of value.